Piloting IFC Model Reception on One Project: A Step-by-Step Walkthrough
Before changing how a whole company receives models, try it on one project. The steps of a reception pilot, as we ran them on the Hotel Vela test project with real IFC files: what to set up, what to measure and what to expect in the first weeks.
Reception inbox of the Hotel Vela test project with seven deliveries and the first step of the guided demo: a supplier delivers a model
Nobody changes how a whole company receives models in one go. The sensible way is one project, three or four suppliers, a few weeks. These are the steps, as we ran them on our Hotel Vela test project with real IFC files from the architecture, structure and MEP models.
Key takeaways
- One project, three or four suppliers, four to six weeks.
- Agree the requirements and the naming before the first delivery, not after.
- Measure three numbers: accepted the first time, days to decide, calls per return.
- Switch on automations only once the manual decisions look right.
Step 1: the requirements
Create the project with a minimum score, your rules and the ISO 19650 naming convention: in our test, project code HVL, minimum 80, delivery due on Thursdays at 12:00. If you are not sure what to require, start with IFC acceptance criteria. Test the rules before anyone receives them: writing and testing your own rules shows how.
Step 2: invite the suppliers
Each supplier gets a link of their own, shown once. Send it the way you already talk to them. In our test there were four: architecture, structure, MEP and façades.
Step 3: the first deliveries
Suppliers check in their browser and send. What arrives in your inbox is already validated: score against the minimum, name check, accepted or returned. In our test, six real files arrived; a ZIP renamed as .ifc was returned before validation. The supplier side is described in an upload page for suppliers without an account.
Local test of the workspace on our own server with the Hotel Vela test models (real IFC files), Spanish interface. Not open yet.
Expect the name check to fail a lot in the first week. In our test every early file used the old project code; only the delivery made through the link with the agreed name passed. That is the point of the pilot: the convention gets fixed once, not argued about at every delivery.
Step 4: decide, with reasons
Open a delivery, compare it with the previous version, accept or return it with a reason. The reason goes back to the supplier's page; the decision is sealed with the file's fingerprint.
Step 5: the log
Every delivery and decision is logged and chained. At the end of the pilot, export it: it is the record of what each supplier delivered, and when. Why that matters is in who sees which model in a delivery CDE.
Step 6: automations, last
Once the manual decisions look right, let the routine ones run alone. In our test, a rule that watches for deliveries under 95 placed an email for the site manager in the outgoing queue each time it matched. The queue never sends anything until sending is switched on.
Local test of the workspace on our own server with the Hotel Vela test models (real IFC files), Spanish interface. Not open yet.
What to measure
| Measure | How | What a good pilot shows |
|---|
| Accepted the first time | Share of deliveries accepted without a return | It rises from the first to the third delivery of each supplier |
| Days to decide | Median from delivery to decision | Decisions in the same week, not at the next meeting |
| Calls per return | Count the calls that follow a return | Fewer: the reason and the fix travel with the return |
The workspace computes the first two; the third you count yourself.
What the pilot will not show yet
- Emails to suppliers and to the client wait in the queue; sending is switched off.
- Watched folders on SharePoint or Google Drive are tested with a stand-in, not yet with real accounts.
- The weekly report for site management still uses sample data.
Run it with us
If you receive models from several suppliers and want to try this on one project, talk to us about a pilot. If you would rather look first, open the guided demo or the page for contractors.